MEP WORKS

MEP Works - Munduk Resort

Buleleng, Bali 2026

MEP works at Munduk Resort Zone 1 are at rough-in stage, with plumbing, fire protection, electrical and external utility pipe installation in progress and testing and backfilling still pending.

MEP Works - Munduk Resort project image

Project overview

Show installation work in progress across four packages: plumbing and drainage, fire protection, electrical rough-in, and external underground utilities. Inside the building, clean-water pipes, drainage stacks and collector lines, red fire protection pipes, electrical conduits, junction boxes and cable runs are installed under the slabs and beams. A ceiling frame has started in one room. Outside, utility pipes (black HDPE and green pipes) are laid in an open trench along the pathway, with jointing works in progress. Overall, the work is at rough-in and installation stage. Testing, trench backfilling and ceiling closing have not yet been carried out. PPE is in use and warning signage is placed at the work area.